Overall experience of 25 years of professional experience in the Mechanical, civil construction industry worked in various disciplines throughout the career in execution of major Electronics industry is construction and maintenance of semiconductor production facilities tool installation, cleanrooms and laboratories, mechanical facility services and HVAC Systems for various facilities and Oil &Gas, building construction. Throughout I, carrier in EXYTE Tool install project supervisor, senior Supervisor now as a construction manager. Responsible for ensuring site safety is maintained according to the safety plan, maintaining the daily progress goals, ensuring installation quality is monitored during the entire construction period, and communicating to Project Managers. Unique challenges daily, with the responsibility of keeping a project on schedule and on budget. Acts as the Company’s representative when dealing with vendors, subcontractors, and other stakeholders.

Overview

26
26
years of professional experience

Work History

Construction Manager

EXYTE Singapore Pte Ltd
02.2023 - Current
  • Company Overview: EXYTE Delivering sustainable solutions for high-tech Facilities to enable clients to provide innovative products and services that enhances the quality of modern life
  • Responsible for communicating and upholding safety culture and safety policies and procedures throughout the project
  • Assists Pre-construction with estimating and pre-construction services and other duties as assigned by the Procurement and Construction Team
  • Works with Procurement in scope of work development and the solicitation and pre-qualification of Subcontractors and Suppliers
  • Responsible for all technical evaluations of bid proposals and overall scope ownership
  • Prepares and manages construction schedule and daily planning of work
  • Be intimately familiar with Subcontractor scope of work, Subcontract agreements, and design drawings, for the ownership of construction execution on time and within budget
  • Responsible for subcontract pay applications reviews and approvals
  • Coordinates with Quality Control and Document Control to ensure the timely review and processing of shop drawings and required submittals in a timely manner
  • Coordinates submittals and RFI with Field Engineer or responsible design professionals
  • Coordinates, communicates, and documents changes in scope of work
  • Responsible for capturing and communicating any schedule, quality, or cost associated with changes
  • Coordinates with the Superintendents and Quality Control all required testing, and documentation is planned and completed correctly
  • Ensures Quality is upheld daily, and punch lists are generated and completed in a timely manner
  • Develops and maintains continuous positive relationships with the Client and their representatives
  • Promotes positive staff morale, professionalism, and attitude, and assists to resolve potential deficiencies when identified or perceived
  • Participates in continuous improvement plans as directed and/or through proactive application of personal expertise
  • Maintains a thorough knowledge and understanding of the company’s project processes, procedures, and policies and is responsible for enforcing the use and conformance thereof
  • Ensures that Project Controls are maintaining the Contract Documents
  • Ensures are always up-to date, with all revised drawings, addenda, and Change Orders
  • Ensures all project closeout documentation, including project as built are continuously maintained
  • Assists in preparation of all project status reports
  • EXYTE Delivering sustainable solutions for high-tech Facilities to enable clients to provide innovative products and services that enhances the quality of modern life

Senior Mechanical Supervisor (Tool Install)

EXYTE Singapore Pte Ltd
07.2014 - 01.2023
  • Project Monitoring and progress report for the installation and tie in for all the mechanical systems
  • Verify for engineering construction drawings (VMP & LSP), estimates and installation of hookup works
  • Field verification of all mechanical and electrical POC locations pop out management, Space management, interacting with engineering and clients, attending review meetings
  • Attend daily meetings with Client, Tool owners to update progress if there any changes on design and schedule
  • Coordinate and contact daily Whiteboard meetings with sub-contractors, tool owners and vendors, to update the progress
  • In addition, execution of construction team and liaise with sub-contractors such as scaffold, sprinkler, and Partition work
  • Verify and layout datum’s in sub-fab for support equipment
  • To provide as built drawings to client the design changes and site installation
  • Ensure contractor following safe work procedure and educating to work safe
  • Confirm the pipelines (services) according to SUD (standard utility detail) and P&ID, update tagging matrix & P&ID
  • Walk down with clients and clear the outstanding punch list for the system completion and hand over etc
  • Execution to ensure the tool turn on schedule & Indent Quality to satisfy customer requirement
  • Plan and execute equipment hookup for new, conversion, unhooking and relocation tools
  • Plan, track and update utilities progress updates to project manager
  • Monitors work area to ensure quality and process standards are being followed
  • Resolves day-to-day tool install activities and design issues
  • Manage contractors to follow in house protocol and follow up work assignment base on manpower availability to meet construction schedule
  • Cost sheets walk down with client and contractors
  • Other duties performed Base Build / Tool Install space management coordination

Mechanical Engineer

SAMSUNG C &T CORPORATION
05.2012 - 06.2014
  • Company Overview: Samsung C&T Corporation is global construction company whose business involves the design and building, EPC of Oil & Gas high-tech facilities, residential building, and power plants
  • Review of Engineering drawings and Project Planning schedule and plan weekly work TOP schedule and discuss with subcontractors for execution of the work
  • To manage the sub-contractors and monitor site installation progress to achieve project completion within time with appropriate safety norms
  • To arrange for testing of M&E equipment functional test, liaise with consultant in solving technical and detailing issues of M&E works
  • Coordinate all M&E related issues with the Project Engineer and Architectural Supervisor
  • To plan daily & weekly work schedule and discuss with subcontractors for execution of the work and report to project manager
  • Coordination with client, consultants / designer and sub-contractor suppliers and vendors for project execution and ensure the safety norms are followed by everyone
  • Liaise with in-house Design Consultants for any Design & Build Tender in connection with Mechanical Works
  • Samsung C&T Corporation is global construction company whose business involves the design and building, EPC of Oil & Gas high-tech facilities, residential building, and power plants

Mechanical Supervisor (Tool Install)

M+W GROUP
10.2010 - 03.2012
  • Responsible for project Walk-down with sub-contractors and Clients to mark the location as per LSP for the routing of utility services (Gas lines, vacuum lines, and cable Trucking)
  • Coordination with area engineer for drawing changes and other engineering issue
  • Involve in everyday white board meeting and coordinate with all contractors for the prefabrication and installation of utility lines and reminder to work quality & safety
  • Attending weekly construction meeting with contractors and Clint
  • Closely monitor manpower for the allocated area
  • Coordinate with relevant contractors and Clients for the inspection of Datum marking for incoming tools
  • Coordinate with logistic teams for mobilization and installation of Tools
  • Coordinate with contractors and client for the Hook-up (Tie-in) of pipelines after completing the pressure test
  • Confirm the pipelines (services) according to SUD (standard utility detail) and P&ID and update tagging matrix & P&ID
  • Walk down with clients and clear the outstanding punch list for the system completion and hand over etc

Piping Supervisor

ROTARY ENGINEERING LIMITED
07.2006 - 09.2010
  • Company Overview: An EPC company in Singapore in the field of Engineering, Oil & Gas, Power, One of the Leading Company in Singapore
  • Site Engineer, performed under the direction of Project Manager for piping fabrication, Fire protection system, HVAC Systems for various facilities, water and sanitary, structure cabling, fire alarm, Wastewater management, Chiller package system and structural steel erection of OSBL area and Administration building, Main substation
  • Coordination with engineering, procurement, and Construction-Team
  • In addition, execution of construction team and liaise with sub-contractors such as insulation, blasting, and painting etc
  • Attending weekly meetings with Clint, vendor, and sub-contractors
  • Review, co-ordinate and generate subcontractor’s M&E shop drawings as and when necessary
  • Has worked three months in testing, commissioning, and system-hand over
  • Project supervising in fabrication / installation of product pipelines, utility pipeline, Potable water pipelines, and fire water pipelines in Mono Ethylene glycol (MEG) project
  • Monitoring receiving materials, fabrication, and erection as per latest ISO drawing
  • Attending daily and weekly construction meeting
  • Isolation valve list, line checking of system as per latest P&ID for construction and client issues Drawings
  • Ensuring safe working procedure and educating the workers about safety
  • Monitor during of inspection & Quality Control with compliance to various standards and specification for the project
  • Report daily progress to immediate supervisor and prepare materials, manpower and equipment’s day-by-day activity
  • Coordinate with welding supervisor and area QC inspector to inspect fit-up and welding inspection
  • Planning of erection sequence as per site condition
  • Monitor during of inspection & Quality Control with compliance to various standards and specification for the project
  • Instruct and advise to workers about safety, quality, and productivity
  • An EPC company in Singapore in the field of Engineering, Oil & Gas, Power, One of the Leading Company in Singapore

Piping Supervisor

INTERWIDE TECHNOLOGY PTE LTD
09.2002 - 06.2006
  • Maintenance work for Ship pipe modification and piping erection activity
  • Preparation and Co-ordination for final assembly and Hydro test clearance
  • Preparation of as built drawing and co-ordination with customer to obtain the approval
  • Execution to ensure the production schedule & Indent Quality to satisfy customer requirement
  • Co-ordination with QC department for inspection of materials and release note for fabrication
  • Co-ordination with sub-vendors for NDT activities and other related agencies
  • Punch list Preparation based on P&ID and other drawings for mechanical completion to do hydro test
  • Manpower allocation for day-to-day activities

Assistant Engineer

Chaitanya Contractors & Eng Pvt Ltd
06.1998 - 07.2002
  • Supervising of Fabrication, Erection, and testing of piping works
  • Supervising of equipment erection, Alignment, and related structural steel
  • Crosscheck ISO with plan and P&ID drawing
  • Prepare as built drawing, as built control sheet and other related documents
  • Report to Engineer on job progress
  • Coordinate with Sub-Contractor
  • Mechanical inspection of the system as per P&ID
  • Submitting daily progress reports to immediate superiors
  • Final submission of related QC documents to the client
  • Tractability Fit-up, visual
  • Reports

Education

Diploma - Mechanical Engineering

State Board of Technical Education and Training
Chennai, Tamil Nadu

Skills

  • MS Office

Languages

English
Tamil

Personal Information

  • Date of Birth: 07/12/78
  • Nationality: Indian

Disclaimer

I declare that the above-mentioned details are true to the best of my knowledge., Current Date, Singapore

Nric

S7885841I

Timeline

Construction Manager

EXYTE Singapore Pte Ltd
02.2023 - Current

Senior Mechanical Supervisor (Tool Install)

EXYTE Singapore Pte Ltd
07.2014 - 01.2023

Mechanical Engineer

SAMSUNG C &T CORPORATION
05.2012 - 06.2014

Mechanical Supervisor (Tool Install)

M+W GROUP
10.2010 - 03.2012

Piping Supervisor

ROTARY ENGINEERING LIMITED
07.2006 - 09.2010

Piping Supervisor

INTERWIDE TECHNOLOGY PTE LTD
09.2002 - 06.2006

Assistant Engineer

Chaitanya Contractors & Eng Pvt Ltd
06.1998 - 07.2002

Diploma - Mechanical Engineering

State Board of Technical Education and Training