Having Professional experience of seven Years in Construction projects, shutdown work piping, equipment’s and running maintenance works. Able to handle work under pressure, stay focused on work what need to be done and quick learner with an opportunity to contribute towards the growth of self as well as organization.

Overview

5
5
years of professional experience
1
1
Certification

Work History

Munsiong Engineering Ltd
  • The company is one of the leading of providing Refinery plant maintenance services and turnkey projects in piping and steel structure fabrication, Static and rotating equipment maintenance

Infineum Singapore Pte ltd
  • Jurong Island) Singa Phase II Extension project
  • Roles and Responsibilities
  • Preparing inspection testing plan for all welding activities
  • Conducting material inspection and material traceability
  • Prepare, review of Welding Procedure Specifications (WPS) based on ASME and EN Standards
  • Conduct a welding procedure and welder qualification tests
  • Coordinate with client inspector for site & workshop inspection activities for piping, structural and equipment like heat exchangers pressure vessel ,column
  • Review the calibration status and keep a calibration log of test equipment
  • Verify in process inspection, final inspection and welding
  • Carry out Welding control and inspection
  • Record result of inspections and maintain records of specific items as per client specifications
  • Raise RFI request to Client and 3rd party and coordinate for inspection as identified ITP hold points
  • Reviewing incoming material with Mill test certificates, Dimensional check and physical condition check
  • Checking and verifying of receiving materials (pipes, flanges, fitting, Valves & Equipment, etc,,) as per MTO, ensure that materials are correct according to the specification and description upon received
  • Conduct inspection during all phases of fabrication, prior welding, during welding and after welding preparing Daily Welding Reports (DWR)
  • Witnessing non destructive testing (NDT) activities to follow up and confirm repairs, re-testing and re-inspection in accordance with specifications
  • Witnessing post weld heat treatment (PWHT), Heating method & temperature record system
  • Witnessing positive material identification (PMI), verify that all PMI of material has been performed as per specification
  • Reviewing of RT, UT, MT, PT, PMI, PWHT & Hardness Test Reports
  • Preparing welding surveillance report as per client requirement
  • Prepare the of weld & NDT summary
  • Completing/Endorsing all inspection records from initial inspection to final acceptance of weld joints
  • Conduct Alignment Inspection of Static & Rotary equipment
  • Physically Verify the Pumps Discharge and Section Nozzle orientation
  • Verification of Shell and Roof Nozzle Orientation and Installation of Tank equipment’s internally and externally such as Level gauge, Breather valve, Foam seal etc
  • Coordination with Client/its Representative /Third party inspector/ Suppliers for inspection requirements of the project
  • Review hydro-test procedure and preparing hydro-test packages and spool release & Weld History documents
  • Ensure that calibration certificate of test instruments such as pressure gauge, relief valve, manifold, pressure and temperature recorder prior to hydro test
  • Ensure that the correct rating gaskets are installed
  • Ensure that the A- punch list items Shall be closed before hydro test
  • Witnessing & visual Inspection of pipe Line internal cleaning /gauging
  • Witnessing valve Hydro test in different ratings
  • Witnessing valve installation, spool installation and bolt tightening
  • Witnessing of pneumatic test, hydro-test, flushing
  • Line check before commissioning activities and assist in Punch list preparation and punch list items closing
  • Coordination with construction Team for Re-Instatement activities
  • Preparing and maintaining QA/QC documents and final test packages for system lay-up.

Quality Control Supervisor

Bilfal Heavy Industries Ltd
06.2012 - 12.2013
  • The company is one of the leading constructions of Pressure vessel, Storage tanks, Heat exchangers, piping, Project Handled: Samsung Vessel project, Power Gas piping project
  • Roles and Responsibilities
  • Preparing inspection testing plan for all welding activities
  • Conducting material inspection and material traceability
  • Prepare, review of Welding Procedure Specifications (WPS) based on ASME and EN Standards
  • Conduct a welding procedure and welder qualification tests
  • Coordinate with client inspector for site & workshop inspection activities for piping, structural and equipment like heat exchangers pressure vessel ,column
  • Review the calibration status and keep a calibration log of test equipment
  • Verify in process inspection, final inspection and welding
  • Carry out Welding control and inspection
  • Record result of inspections and maintain records of specific items as per client specifications
  • Raise RFI request to Client and 3rd party and coordinate for inspection as identified ITP hold points
  • Arrange for proper NDT requirements as per specifications
  • Review all NDT reports and get approval from client
  • Witnessing all testing activities as required by approved Inspection and Test plan
  • Monitoring PWHT activities carried out as per approved procedure
  • Performing line walk and punch listing with client inspector
  • Preparing Test Packs for Piping Hydro static testing
  • Prepare/compile final punch list prior to handover
  • Hand over final documentation to client.

Quality Control Supervisor

Mabel Engineers pvt Ltd
04.2009 - 05.2012
  • The company is one of the leading constructions of Pressure vessel, Storage tanks, Chimney, Reactor, Power plant structures and piping, Project Handled: TNPL Tank and piping Project, LTL Bangladesh Power plant project, VRV India Cryogenic outer jacket vessel project, DCW Pressure Vessel project
  • IT SKILLS
  • COMPUER PROVICENCY
  • Possess working knowledge in Windows, MS-Office
  • Possess working knowledge in AutoCAD

Quality Control Supervisor

Pit Stop
03.2014 - 1 1
  • Projects handled : PU2-Loc, project, Flare Project, IW Phase II project, maintenance jobs in piping and static equipments, ECC DBN project with shutdown, CD5 Shutdown project, CD4 Shutdown piping, SRU-6 Shutdown piping CD3 Shutdown piping

Education

SSLC -

Don Bosco higher secondary school

B.E - Mechanical Engineering

Shri andal alagar college of Engineering
2009

-XII - undefined

Anna University
2005

HSC - undefined

Don Bosco higher secondary school
2003

Skills

  • Ultrasonic testing(UT)
  • Radiography testing (RT)
  • Penetrant testing(PT)
  • Magnetic particle testing (MPT)

Certification

Having Certified CWSIP 3.1(TWI-UK) Welding inspector (ID: 354092) Having Certified ASNT Level – II in Nondestructive testing as per standard SNT–TC–1A

Timeline

Quality Control Supervisor

Pit Stop
03.2014 - 1 1

Quality Control Supervisor

Bilfal Heavy Industries Ltd
06.2012 - 12.2013

Quality Control Supervisor

Mabel Engineers pvt Ltd
04.2009 - 05.2012

Munsiong Engineering Ltd

Infineum Singapore Pte ltd

SSLC -

Don Bosco higher secondary school

B.E - Mechanical Engineering

Shri andal alagar college of Engineering

-XII - undefined

Anna University

HSC - undefined

Don Bosco higher secondary school
V. Bharath Kumar