Senior Tunnel Engineer
China Communications Construction Company Ltd. (Singapore Branch)
04.2022 - Current
PROJECT: CR109 Design and Construction of Tampines North Station and Tunnels for Cross Island Line
Responsibilities:
Manage staff relationship; develop communication link between Sub cons on Site
Ensure all activities are properly planned and coordinated, including coordination with Interfacing Contractor as well as taking over and handing back of interface area used for tunneling works.
Addition SI and Ground Improvement works
Lead tunnel team and provide them opportunities to improve their working skill and continuously improve their teamwork values
Responsible for TBM progress and execute daily tunnel work programme for initial drive ,main drive and report to Tunnel Manager
Responsible to check and control the TBM parameters
Review, suggest and adjust TBM parameters and operation parameter injection with the ground monitoring reading to the Tunnel Manager.
Responsible to plan and manage of shifting tunnel crew allocation and ensure smooth handing over between shifts
Implemented quality control measures to ensure adherence to safety and regulatory standards.
Developed project schedules, budgets, and resource allocations for multiple concurrent projects.
Senior Tunnel Engineer
Ed. Zublin Ag
01.2019 - 03.2022
PROJECT: DTSS2 T07 – Proposed Construction of Sewer Tunnels for the Deep Tunnel Sewerage System Phase 2 Project.
Responsibilities:
Manage staff relationship; develop communication link between Sub cons on Site
Ensure all activities are properly planned and coordinated, including coordination with Interfacing Contractor as well as taking over and handing back of interface area used for tunneling works.
Ground Improvement works
Drain diversion works, decking for site access
Shaft Construction works top down method by in situ wall construction.
Sheet piling works and soil excavation for site works
Lead tunnel team and provide them opportunities to improve their working skill and continuously improve their teamwork values
Responsible for TBM progress and execute daily tunnel work programme for initial drive ,main drive and report to Tunnel Manager
Responsible to check and control the TBM parameters
Review, suggest and adjust TBM parameters and operation parameter injection with the ground monitoring reading to the Tunnel Manager.
Led engineering teams in design and execution of large-scale infrastructure projects.
Mentored junior engineers, fostering professional development and enhancing team capabilities.
Senior Tunnel Engineer
SSANGYONG -Hyundai Joint Venture
06.2017 - 11.2018
PROJECT: Construction of Marine Terrace Station and Tunnels for Thomson East Coast Line The construction of Marine Terrace station (T308) and its associated tunnels
Responsibilities:
Prepare method statement , submit and review comments
Review, suggest and adjust TBM parameters and operation parameter injection with the ground monitoring reading to the Tunnel Manager
Responsible to ensure and execute the quality control procedures in tunneling works. Review and implement if necessary
Provide necessary guidance, direction and supports to both senior and junior staff so that they are able to accomplish their goals and jobs effectively; to liaise with subcontractors to resolve tunneling problems.
Report to Tunnel Manager and communicate with the client and QP(S) to ensure the available information related to tunneling works is clear and accurate.
Ensure all tunneling activities are properly planned and coordinated, including coordination with Interfacing Contractor as well as taking over and handing back of interface area used for tunneling works.
Deputy Tunnel Manager
DAELIM Industrial.co. Ltd
05.2015 - 04.2017
PROJECT: Construction of Outram Park Station and Tunnels (1.13Km) for Thomson East Coast Line The construction of Outram Park station (T222) and its associated tunnels
Responsibilities:
Prepare method statement , submit and review comments
Review, suggest and adjust TBM parameters and operation parameter injection with the ground monitoring reading to the Tunnel Manager
Responsible to ensure and execute the quality control procedures in tunneling works. Review and implement if necessary
Provide necessary guidance, direction and supports to both senior and junior staff so that they are able to accomplish their goals and jobs effectively; to liaise with subcontractors to resolve tunneling problems.
Report to Tunnel Manager and communicate with the client and QP(S) to ensure the available information related to tunneling works is clear and accurate.
Manage staff relationship; develop communication link between tunnel team and the Management; assign tasks to respective Shift Engineer
Ensure all tunneling activities are properly planned and coordinated, including coordination with Interfacing Contractor as well as taking over and handing back of interface area used for tunneling works.
Lead tunnel team and provide them opportunities to improve their working skill and continuously improve their teamwork values. Dismantling of TBM and retrieval works.
Developed strategic plans aligning project objectives with organizational goals, enhancing overall performance.
Unknown pile extraction works
Senior Tunnel Engineer
PENTA-OCEAN Construction Co. Ltd
07.2013 - 03.2015
PROJECT: Contract 933 is for the construction of Bendemeer station and associated tunnels for Down Town Line Stage 2
Responsibilities:
In charge of TBM and tunnel drives by Tunnel Manager
Responsible for TBM progress and execute daily tunnel work programme for initial drive ,main drive and report to Tunnel Manager
Responsible to check and control the TBM parameters
Review, suggest and adjust TBM parameters and operation parameter injection with the ground monitoring reading to the Tunnel Manager.
In-charge of reconciliation of excavated spoil
Responsible to plan and manage of shifting tunnel crew allocation and ensure smooth handing over between shifts
Responsible to ensure and execute the quality control procedures in tunneling works. Review and implement if necessary.
Collate, check and review all the forms with Tunnel Shift Engineer pertaining to tunneling. TBM retrieve works and First Stage Concrete work
Senior Tunnel Engineer
Alpine Bau GmbH
08.2012 - 06.2013
Project: Contract 917 & 918 for the Design and Construction of Sixth Avenue King Albert Park and Tan Kah Kee stations and tunnels for construction of Circle Line 3 and 4.
Senior Tunnel Engineer
Sembawang Engineers & Constructors
02.2011 - 07.2012
Project: Contract 919 for the design and construction of Stations and Tunnels at Botanic Gardens and Stevens Stations for downtown line stage 2.
Site Engineer
SSANGYONG Engineering & Construction Co. Ltd
11.2009 - 02.2011
Project: Contract 921 for the design and construction of Rochor and Little India stations and associated tunnels
Tunnel/Site Engineer
WH-STEC-AM-JV
12.2008 - 09.2009
Project: WH-STEC-AM JV, (Contract 855). It is a joint venture of three companies (WOH HUP PRIVATE LIMITED, SHANGHAI TUNNEL ENGINEERING COMPANY LIMITED & ALPINE MAYREDER Bah GmbH). Organization working in Singapore MRT Contract 855. It's working on the construction of Approx. 4 Km of twin bored tunnels and 350m of cut and covers tunnels, four metro stations (Kent Ridge MRT, One North Station, and Buona Vista MRT & Holland Village MRT).
Tunnel Engineer
Sembawang Engineers and Constructors
07.2007 - 11.2008
Project: Sembawang Engineers and Constructors (C856) Construction and completion of West coast, Pasir Panjang, Alexandra and Telok Blangah stations including HarbourFront station fit out works and Tunnels.
Site Supervisor
Taisei Corporation
08.2005 - 06.2007
Project: Contract 854 part of the MRT Circle Line Stage 4 and comprises the Construction of some 5.6km single tube twin bored tunnels, 13 numbers of cross passages, 3 numbers of stations and one number RTS structure including short sections of cut and cover tunnels.
Supervisor
Ed. Zublin Ag
10.2001 - 09.2004
Project: Contract T-06 comprises the design and construction of deep sewer tunnel with an excavated diameter of 4.50m, finished internal diameter of 3.30m and total length of 9.6km. In addition, seven permanent access shafts had constructed.
Education
Diploma - Civil Engineering
MOHAMMED INSTITUTE OF EDUCATION AND TECHNOLOGY
Trichirappalli, Tamil Nadu
Skills
Construction Safety Course for Project Managers
Building Construction Supervisors Safety
Building Construction Safety Supervisors(Tunneling)Course
Confined Space Rescue Course
Construction Safety Management Course
Languages
English
Advanced (C1)
Hindi
Intermediate (B1)
Disclaimer
I hereby declare that the foregoing information provided by me is true and I shall stand by the same.
PERSONAL PROFILE
Date of Birth : 19th May 1979
Father's Name : Kaleel Rahman
Marital Status : Married
Immigration Status : Singapore PR
Nationality : Indian
NRIC No : S7966069E
Passport No : Z7712867
Timeline
Senior Tunnel Engineer
China Communications Construction Company Ltd. (Singapore Branch)
Finance Executive at China Communications Construction Company Ltd. (Singapore Branch)Finance Executive at China Communications Construction Company Ltd. (Singapore Branch)
Assistant Planning Manager at China Communications Construction Co. Ltd. (Singapore Branch)Assistant Planning Manager at China Communications Construction Co. Ltd. (Singapore Branch)
Chinese Translator Cum Field Operator at Power China Jiangxi Electric Power Construction Company Dubai BranchChinese Translator Cum Field Operator at Power China Jiangxi Electric Power Construction Company Dubai Branch