E&I Superintendent with extensive experience at MODEC Offshore, specializing in compliance inspections and project management. Demonstrated success in improving quality control processes and promoting teamwork, leading to successful project completions. Skilled in documentation and risk assessment, contributing to operational excellence and adherence to safety standards.

Overview

20
20
years of professional experience

Work History

E&I Superintendent

MODEC Offshore
08.2014 - Current
  • Provide co-ordination between supervisors, engineering and E&I subcontractors, vendors and fabrication yard.
  • Complete the discipline scope safely and monitor field construction activities to ensure design requirements are met in compliance with drawings, specifications, and applicable codes.
  • Ensure that adequate risk assessments are carried out and steps are taken to minimise risks on site. Verify safe working procedures are established and supervise correct implementation.
  • Attend daily VSCC meeting with Project and Subcontract personnel.
  • Responsible for guidance to supervisors for verification/inspection of the entire scope within discipline, ensuring they are fully familiarized with project requirements, monitoring subcontractor’s performance and providing feedback.
  • Supervising subcontractor E&I supervisors, ensuring they are fully familiarized with project requirements, monitoring subcontractor’s performance and providing feedback.
  • Inform mechanical completion group and/or Completion Database lead of any deficiency in work performance
  • Monitor and verify all mechanical completion within the discipline.
  • Work in close cooperation with the mechanical completions group and participate in final completion check out and approval of Inspection and Test Records (ITR’s).
  • Assist in maintaining the punch list and assist in verification of items completed.
  • Assist in obtaining scope descriptions of any punch list item being transferred as carry over work within his discipline.

Supplier Quality Engineer

MODEC Offshore
08.2014 - Current
  • Be One team approach.
  • Timely issuance of IRC’s
  • Engagement with TPI’s and minimize the Punch list on receipt.
  • Timely review of vendor documents
  • Be proactive, timely decision and collaborative.
  • No major Noncompliance left unidentified.
  • Clear Communication / company’s goals and contributes to those objectives. Regular meetings, detailed briefings
  • Timeline Management / Establish clear timelines and deadlines for reaching milestones.
  • Continuous Monitoring / regulatory changes

HAE Coordinator & Lead Ex Inspector (CompEx)

MODEC Offshore
08.2014 - Current
  • Focal point of contact on Hazardous Area matters on the project.
  • Ensures ECIT systems and components adhere to relevant regulation and standards.
  • Conducts thorough inspection and functional tests of electrical, instrumentation and telecoms equipment and systems to verify compliance with design specifications, codes and standards.
  • Maintains comprehensive documentation and records for hazardous area equipment and its certifications.
  • Provides guidance and functional support to personnel involved in the inspection and testing of the ECIT systems.
  • One team approach
  • Achieving your KPI. (Surveillance & others)
  • Be proactive, timely decision and collaborative.
  • Maintain Quality Integrity.
  • No Major quality issues in Yards left unidentified & leading to Cost & schedule delays.
  • No failure in Chapter IX compliance. (Piping)
  • Taking lead on quality and going beyond to support project.
  • Responsible for Overall Marine & Topside Modules (Includes Vendor Packages) and integration Phase (China & Brazil) scope of work includes (Planning, Managing, Supervision, work scheduling & Co-Ordination to be carried out Ex inspection, Periodic inspection, HAE Audit & System Responsible Person-SRP for system completion)
  • Initial Verification from design phase to ensure all engineering approved HAE equipment’s are comply with Hazardous Area Classification and in respective to IEC & ATEX. Through Ex register
  • First-Article Inspection to ensure each equipment installation take place (As a sample), to ensure to check and confirm 100% product outcome based on approved PO, Design spec, Modec Specs, IEC & ATEX Compliance, includes acoustic glanding and apparatus, prior to installing the remaining equipment’s on board with sub-contractors/integration yard and ensure all equipment’s installation and outcome for the ATEX Inspection to meet the requirement
  • Installation, set-up and commissioning of Process Electrical & Instrumentation.
  • Installation, testing and inspection of Electrical Equipment in Hazardous Areas (ATEX).
  • HV and LV Equipment inspection and testing, PTW, Process Isolations, Electrical Isolations & Gas Test Atmospheres
  • Initial Detailed Hazardous Area Equipment’s (HAE) Inspections of all Electrical and Instrumentation systems to ensure compliance with relevant standards including BS/EN, IEC 60079, and applied latest code and Standards as well as the equipment’s own Ex Certification requirements. Completing inspection reports, punch lists & other documentation requirements
  • Visual, Close and Detailed inspections of all Electrical and Instrumentation Equipment to IEC 60079 & ATEX Guidelines, latest codes of Standards with cross referencing to European standards
  • Several Audit were carried out to ensure the ATEX Inspection performed according to IEC 60079
  • System Responsible for various marine and topside systems, coordinate to complete readiness includes Gas Turbine Generator, Co2 Compressor, Main A & Main B Compressor, VRU and Refrigeration Package

E&I Engineer

Sembawang Shipyard Pte Ltd
07.2007 - 08.2014
  • Review commissioning master schedule. Conduct project progress meetings and set Review and comment on Project Quality Plan, Inspection and Test Plan (ITP) and Project Specific ProceduresReview contractor procedures/drawings to ensure compliance to specification and audit contractor's QA/QC documentation and implementation at site to ensure latest document being circulated and used.
  • Inspect/verified construction/installation of electrical and instrument facilities in platform to ensure full compliance to design specification
  • Conducting MC meetings & expediting various fabricators for progress of mechanical completion.
  • Resolve site technical queries related to construction, testing and pre-commissioning.
  • Witness factory acceptance tests for all electrical Equipment
  • Ensure all E&I calibration work on protection relays, current injection test on thermal overloads, valves stroking, transmitters, psv and switches are performed and documented accordingly.
  • Raising NCR in case of non conformance observed and follow up for NCR closer
  • Preservation has been executed and signed off.
  • Coordinated with commissioning team to fix system boundaries & finalize system-subsystem list.
  • Perform line check as per P&ID & ensure system readiness and mechanical completion of system prior handing over to final commissioning.
  • Architectural (Outfitting) experience and knowledge includes design verification, class rules, material verification and site QAQC inspection untill accomodation handover, including HVAC System
  • Piping experiences and basic knowledge to carry out piping inspection, includes P&ID Line walk, material verification, process safety and welding checks, pressure testing of piping system, installation of structural steel, pressure vessel, tanks, relief valves and rotating equipments.
  • Structural Knowledge and experience includes WPS assesment, PQR review, welding inspection, tank testing inspection
  • PRE-COMMISSIONING EXPERIENCE:- Check the readiness of engine auxiliaries systems which includes powering up & commissioned the system respectively:
  • COMMISSIONING EXPERIENCE:- GENERATOR / SWITCHBOARD / TRANSFORMER and Breaker Protection settings, setting / adjust Automatic Voltage Regulator (AVR) settings for generator, Generator voltage setting, Generator sequence checking, Generator frequency setting, Monitoring generator parameters as per manufacturer requirements
  • To conduct load test of individual Generator and testing of load share units, conducting Droop and synchronous load sharing mode tests with PMS & Load bank sizing for load test. Single Generator load test, Parallel load test, Step load test, Load rejection test
  • SEA-TRIAL SCOPE: - FMEA Test, Thruster Sea trial Test (Maneuvering Test, Crash stop Test, Endurance test), UPS back up test, External communication device test, PMS/AGS/SAT
  • Test (Blackout Recovery Test, Black Out Preventer Test), To perform and validate above mentioned activities to meet design philosophy to satisfy owner & certifying authority including marine system, safety system, navigation system, communication system and other system etc.

System Engineer

Singapore Technologies Electronics
04.2005 - 07.2007
  • CIRCLE LINE MRT PROJECT (C830) OPERATION COMMAND CENTRE(OCC)
  • Planning Project Scheduling for Site Testing & Commissioning.
  • Designing and making a checklist for Programmable Logic Controller (PLC) Cabinet for various MRT Stations (Circle Line Projects)
  • Create Schematics Drawings for various MRT stations
  • System Setup and installation
  • Technical Coordination for Systems integration developers.
  • Site Testing & Commissioning
  • Design Single Line Diagram for Various MRT stations (CCL-Circle Line)
  • Strong fault finding and trouble shooting skills related Electrical and Electronics equipment’s
  • Interface, network monitoring system, tool communication system maintenance.
  • Knowledge of Software upgrade, PLC, SCADA system
  • All construction work managed with contractors and vendors.
  • PLC wiring and ladder diagram modification
  • Develop solution to technical problems.
  • Coordinate with contractor and vendor for installation and maintenance.

Education

DIPLOMA - ELECTRICAL ENGINEERING

NGEE ANN POLYTECHNIC
04.2005

HIGHER NITEC - ELECTRICAL ENGINEERING

ITE TAMPINES
06.2002

NTC- 2 - ELCTRICAL TECHNOLOGY

ITE YISHUN
12.2000

NTC- 3 - ELCTRICAL TECHNOLOGY

AVI
12.1999

Skills

  • Compliance inspections
  • Project management
  • Documentation and quality control
  • Teamwork and collaboration

Languages

  • ENGLISH, PROFESSIONAL
  • TAMIL, PROFESSIONAL
  • MANDARIN, BEGINNER
  • PORTUGUESE, BEGINNER

Personal Information

  • Gender: MALE
  • Nationality: SINGAPOREAN
  • Marital Status: MARRIED

Name In Chinese

NIL

Timeline

E&I Superintendent

MODEC Offshore
08.2014 - Current

Supplier Quality Engineer

MODEC Offshore
08.2014 - Current

HAE Coordinator & Lead Ex Inspector (CompEx)

MODEC Offshore
08.2014 - Current

E&I Engineer

Sembawang Shipyard Pte Ltd
07.2007 - 08.2014

System Engineer

Singapore Technologies Electronics
04.2005 - 07.2007

DIPLOMA - ELECTRICAL ENGINEERING

NGEE ANN POLYTECHNIC

HIGHER NITEC - ELECTRICAL ENGINEERING

ITE TAMPINES

NTC- 2 - ELCTRICAL TECHNOLOGY

ITE YISHUN

NTC- 3 - ELCTRICAL TECHNOLOGY

AVI
MOHAMED JAMALUDEEN VALAPPAI ABDUL GAFFOOR